Chart of accounts for a construction company

Omkar Moraye · September 26, 2026 · Updated November 2, 2026
What is the best chart of accounts for a construction company in QuickBooks Online?
A chart of accounts for a construction company separates direct job costs from overhead. Job costs (materials, field labor and its payroll taxes, 1099 subcontractors, equipment rental, permits) sit in 5000-series Cost of Goods Sold, overhead in the 6000s, and retainage and over- or underbillings get their own balance sheet accounts, so each job shows its gross profit.
A chart of accounts for a construction company has one job above all others: keep the cost of each job apart from the cost of running the business. The 42-account version below does that in QuickBooks Online, with the account numbers, Account Types and Detail Types ready to import.
Why standard QuickBooks accounts break construction books
The default QuickBooks Online chart of accounts is generic. It starts with one Cost of Goods Sold account, and most of what a contractor spends ends up in overhead expense lines.
For a general contractor or trade specialty subcontractor (electrical, plumbing, HVAC, framing), that default setup hides project profitability. When direct job materials, field labor, equipment rentals, and 1099 trade subcontractor invoices post to general expense lines alongside the shop rent and office internet, your Profit & Loss statement cannot report whether a specific job cleared its estimated 25% gross margin or bled cash.
A construction chart of accounts uses a numbering system that isolates Direct Job Costs (Cost of Goods Sold) from Operating Overhead (Expenses), creating the structural foundation required for job costing. For complete company preferences and project settings, see our QuickBooks Online construction setup guide.
You can download this complete structure as an Excel workbook:
Download the Construction QBO Chart of Accounts
42-account template with job costing classifications and retainage setup.
The account numbering standard
Account numbers are off by default in QuickBooks Online. To turn them on, go to Settings > Account and settings > Advanced, select Edit in the Chart of accounts section, and turn on Enable account numbers (Intuit, updated August 4, 2026). The ranges below are the ones this template uses:
| Account Number Range | Financial Statement Section | Purpose in Construction Accounting |
|---|---|---|
| 1000 – 1490 | Current Assets | Operating cash, payroll accounts, and contract retainage receivable |
| 1500 – 1990 | Fixed Assets | Work trucks, heavy machinery, trailers, and accumulated depreciation |
| 2000 – 2490 | Current Liabilities | Trade payables, subcontractor retainage payable, and overbillings |
| 2500 – 2990 | Long-Term Liabilities | Equipment notes, vehicle loans, and commercial bank credit facilities |
| 3000 – 3990 | Equity | Owner capital contributions, owner draws, and prior-year retained earnings |
| 4000 – 4990 | Income | Progress billings, approved change orders, and time-and-materials billings |
| 5000 – 5990 | Cost of Goods Sold | Direct Job Costs: materials, field labor, 1099 subs, rentals, permits |
| 6000 – 6990 | Overhead Expenses | Shop lease, general liability insurance, estimating software, legal/tax |
| 7000 – 7990 | Other Income / Expense | Financing interest expense, asset sales gains/losses |
The line that matters is between the 5000s and the 6000s. If an expense is directly tied to a customer contract, it belongs in the 5000-series Cost of Goods Sold. If it would exist even if every job shut down tomorrow, it belongs in 6000-series Operating Overhead.
There is no single official numbering. The National Association of Home Builders publishes its own chart of accounts for builders and remodelers, which some residential builders and their CPAs follow; this template uses simpler four-digit ranges that fit a small QuickBooks Online file.
Complete construction chart of accounts hierarchy
The full 42-account list for general contractors and specialty subcontractors in QuickBooks Online:
| Number | Account Name | Account Type | Detail Type |
|---|---|---|---|
| 1010 | Operating Checking | Bank | Checking |
| 1020 | Payroll Checking | Bank | Checking |
| 1100 | Accounts Receivable | Accounts Receivable | Accounts Receivable (A/R) |
| 1150 | Retainage Receivable | Other Current Assets | Other Current Assets |
| 1200 | Inventory - Direct Materials | Other Current Assets | Inventory |
| 1300 | Costs in Excess of Billings (Underbillings) | Other Current Assets | Other Current Assets |
| 1400 | Prepaid Commercial Insurance & Bonds | Other Current Assets | Prepaid Expenses |
| 1510 | Commercial Vehicles | Fixed Assets | Vehicles |
| 1520 | Machinery & Heavy Job Equipment | Fixed Assets | Machinery & Equipment |
| 1590 | Accumulated Depreciation | Fixed Assets | Accumulated Depreciation |
| 2010 | Accounts Payable | Accounts Payable | Accounts Payable (A/P) |
| 2020 | Commercial Credit Card | Credit Card | Credit Card |
| 2110 | Retainage Payable to Subcontractors | Other Current Liabilities | Other Current Liabilities |
| 2120 | Billings in Excess of Costs (Overbillings) | Other Current Liabilities | Other Current Liabilities |
| 2210 | Payroll Liabilities | Other Current Liabilities | Payroll Tax Payable |
| 2220 | 1099 Backup Withholding Payable | Other Current Liabilities | Other Current Liabilities |
| 2510 | Heavy Equipment Loans Payable | Long Term Liabilities | Notes Payable |
| 2520 | Vehicle Loans Payable | Long Term Liabilities | Other Long Term Liabilities |
| 3010 | Owner’s Capital | Equity | Owner’s Equity |
| 3020 | Owner’s Draws | Equity | Owner’s Equity |
| 3030 | Retained Earnings | Equity | Retained Earnings |
| 4010 | Contract Revenue - Progress Billings | Income | Service/Fee Income |
| 4020 | Change Order Revenue | Income | Service/Fee Income |
| 4030 | Time & Materials Revenue | Income | Service/Fee Income |
| 5010 | Direct Job Materials | Cost of Goods Sold | Supplies & Materials - COGS |
| 5020 | Direct Field Labor | Cost of Goods Sold | Cost of Labor - COS |
| 5025 | Field Labor Burden (Payroll Taxes & Workers Comp) | Cost of Goods Sold | Cost of Labor - COS |
| 5030 | Subcontractor Expense (1099) | Cost of Goods Sold | Cost of Labor - COS |
| 5040 | Job Site Equipment Rental | Cost of Goods Sold | Equipment Rental - COS |
| 5050 | Municipal Permits & Engineering Fees | Cost of Goods Sold | Other Costs of Service - COS |
| 5060 | Dumpsters & Job Site Cleanup | Cost of Goods Sold | Other Costs of Service - COS |
| 5070 | Job Site Safety & Small Tools (< $2,500) | Cost of Goods Sold | Supplies & Materials - COGS |
| 5080 | Freight & Direct Delivery Charges | Cost of Goods Sold | Shipping, Freight & Delivery - COS |
| 6010 | Advertising & Bid Marketing | Expenses | Advertising/Promotional |
| 6020 | Merchant & Bank Wire Fees | Expenses | Bank Charges |
| 6030 | General Liability & Workers Comp Insurance | Expenses | Insurance |
| 6040 | Estimating Software & Office Supplies | Expenses | Office/General Administrative Expenses |
| 6050 | Professional Fees - Legal & Accounting | Expenses | Legal & Professional Fees |
| 6060 | Shop & Storage Yard Lease | Expenses | Rent or Lease of Buildings |
| 6070 | Utilities & Mobile Communications | Expenses | Utilities |
| 6080 | Overhead Vehicle Gas & Repairs | Expenses | Auto |
| 7010 | Business Loan Interest Expense | Other Expense | Other Miscellaneous Expense |
Handling retainage on the balance sheet
In commercial and larger residential work, owners and general contractors commonly withhold 5% to 10% of each progress payment until the job is substantially complete. The contract sets the rate, and some states cap it on public or private jobs.
If you bill $100,000 and the GC holds back $10,000, entering the invoice as an ordinary $100,000 Accounts Receivable balance corrupts your aging reports. The $10,000 retainage shows up as 90+ days past due, even though neither party expects payment until project closeout.
Instead, route retainage through dedicated balance sheet accounts:
- Retainage Receivable (Account 1150): An asset account that records the retainage withheld by your customers. On progress invoices, add a line item that credits contract revenue for the full milestone and debits account 1150 for the 10% retainage holdback, leaving net Accounts Receivable reflecting the true due date.
- Retainage Payable (Account 2110): A liability account that records the 5% to 10% you withhold from your 1099 trade subcontractors until their work is inspected and accepted.
For an in-depth breakdown of how progress billing, retainage, and job costing interact inside QuickBooks Online, see our dedicated guide to bookkeeping for contractors. How the balances in 1300 and 2120 are worked out each month, from a schedule of open jobs, is in our post on WIP in accounting.
Field labor and its burden in the 5000s
Wages for field crews go to 5020 Direct Field Labor. The employer payroll taxes and workers comp premium on those same crews go to 5025 Field Labor Burden, so a job’s labor cost includes what the hour really costs, not just the wage. Office and estimating wages stay in overhead, and so do the general liability policy and the workers comp on office staff (6030). Most payroll providers report employer taxes by employee, which is what makes the split possible each pay run.
Subcontractor 1099 compliance in the 5000s
Trade subcontractors are kept apart from in-house W-2 labor. In QuickBooks Online, post subcontractor bills to 5030 Subcontractor Expense (1099) and mark each of those vendors Track payments for 1099 in the vendor profile.
- Collect the W-9 before the first payment. A deposit or progress payment to a subcontractor without a W-9 on file leaves no taxpayer ID for the 1099.
- Know the 2026 threshold. Form 1099-NEC is required for $2,000 or more paid to a subcontractor in a year for payments made after December 31, 2025, up from $600, with the figure indexed for inflation after 2026. Payments to most corporations are still exempt. Form 1099-NEC vs 1099-MISC covers which form applies.
- Isolate backup withholding. If a subcontractor does not provide a taxpayer ID, the payer must withhold 24% of reportable payments (IRC §3406). Post the withholding to 2220 1099 Backup Withholding Payable and remit it, then report it on Form 945.
The 4 common errors that distort contractor books
- Equipment bought and expensed: Posting a $65,000 truck or skid steer to an expense account swings that month’s P&L into a loss that has nothing to do with the jobs. Record it in 1510 or 1520 and let the CPA decide on Section 179 or bonus depreciation for the return; the MACRS depreciation calculator shows both.
- Customer deposits booked as revenue: A 30% mobilization deposit collected before work starts has not been earned yet. On accrual books it is a liability until the work is billed; depositing it straight to income overstates the first month and leaves the last month of the job showing a loss.
- Crew leads buying materials on personal cards: When foremen buy lumber or fittings on personal cards and no receipt comes back, the job cost is understated and the job looks more profitable than it was.
- No job on the cost line: Every 5000-series line needs the job it belongs to. On QuickBooks Online Plus, Advanced or Intuit Enterprise Suite, set each job up as a project (turn on Organize all job-related activity in one place under Settings > Account and settings > Advanced; Intuit notes it cannot be turned off) and pick the project on every bill and expense line (Intuit, updated October 6, 2026). On Essentials, sub-customers do the same job, and Intuit’s help explains how to change sub-customers into projects later.
The illustrative contractor cleanup (a composite, not a client file) walks through nine months of miscoded job costs, owner draws booked as expenses and an unreconciled equipment loan.
How to import into QuickBooks Online
To check the accounts before importing, search and filter them in the interactive construction chart of accounts explorer.
- Download the
ledgerbrook-construction-chart-of-accounts.xlsxspreadsheet. - In QuickBooks Online, select Settings, then Import data, then Chart of accounts (Intuit: import your chart of accounts).
- Attach the downloaded Excel file and click Next.
- Map the 4 columns: Account Number, Account Name, Type, and Detail Type.
- Review the preview table and click Import.
Common questions about construction accounting
What kind of accounting do construction companies use?
Job costing, on top of ordinary bookkeeping: every cost is tagged to the job that caused it, so each project shows its own profit. Larger contractors keep their books on the accrual basis and recognize revenue on long contracts as the work progresses (percentage of completion), while many small contractors use cash or completed-contract methods for tax, a choice for the tax preparer. The chart of accounts above works under any of them, because job costing lives in the 5000 series and the project tags, not in the method.
Where does construction in progress go on the balance sheet?
Construction in progress is a long-term asset, listed with property and equipment, for something the company is building for its own use, such as a new shop. It is not where client jobs go. Jobs under way for customers are tracked on a WIP schedule, with overbillings as a liability and underbillings as an asset; what is WIP in accounting covers the schedule and its entries.
How do you categorize construction expenses?
Ask one question of each cost: would it exist if this job had never been sold? If not, it is a job cost in the 5000s, tagged to the job: materials, field wages and their payroll taxes, subcontractors, equipment rented for the site, permits, dumpsters, delivery to the site. If it would exist anyway, it is overhead in the 6000s: the shop lease, office staff, estimating software, general liability insurance, advertising. Equipment the company owns is a fixed asset (1510, 1520), not an expense, and interest on the loan that bought it goes to 7010.
Is there a contractor version of QuickBooks?
QuickBooks Desktop Enterprise has a Contractor edition. QuickBooks Online has no separate edition: it handles job costing through projects on the Plus and Advanced plans and Intuit Enterprise Suite, plus the chart of accounts and classes. Intuit Enterprise Suite and Advanced with the construction add-on also offer detailed project costing and phases. QuickBooks Online setup for construction covers the settings.
When contractor books require a professional cleanup
If historical jobs were run without sub-customer tagging, retainage was posted to bad debt, or years of direct materials were lumped into office expenses, a simple chart of accounts import will not fix past balance sheet errors.
Rebuilding job-level history is a QuickBooks cleanup:
$99per month of backlog20% off 6+ monthsIf you are unsure whether your current QuickBooks file supports accurate job costing and progress billing, send your file for a confidential review. Once it is clean, monthly bookkeeping keeps job costs, subcontractor 1099 tracking and retainage reconciled each month.
Published September 26, 2026 · Updated November 2, 2026